RICHMOND — A State Corporation Commission (SCC) hearing examiner
recommends approval of an experimental underground construction of a 230-kilovolt
transmission line in Stafford County. Dominion Virginia Power (DVP) seeks
to construct and operate a five-mile line between Aquia Harbor and a proposed
substation near Garrisonville.
In a report filed on December 12, 2007, Hearing Examiner Michael
D. Thomas found that the construction of the new transmission line on a company-owned
right-of-way is necessary to maintain long-term reliability and to serve the
rapidly growing demand for electricity in the Garrisonville area. The report
serves as a recommendation to the Commission, which makes the final decision.
Thomas observes that the vast majority of residents of Stafford
County understand the need for a new transmission line. However, they prefer
that the line be placed underground. He states that the only real question
for the Commission is whether the new transmission line should be constructed
overhead or underground.
The report notes that there is a sizeable cost differential
between the overhead alternative at $14.16 million and an underground option
at $82.3 million. Thomas recommends the Stafford project as a pilot program
to assess the average cost per mile for the installation of XLPE underground
cable and gain operational reliability and maintenance experience with such
a line. The lessons learned from a pilot program potentially benefit all rate
payers.
Thomas also recommends the SCC should conduct a study of the
impact of overhead transmission lines on real estate values and develop a
methodology for use in Commission cases by which any impact could be analyzed
and valued.
The Commission will rely on the hearing examiner’s report
and the case record to issue a final order. The Commissioners may accept,
modify, or reject the examiner’s recommendations.
###
Case Number PUE-2006-00091